Motorists can expect the Obetsebi Lamptey Interchange to Pamprom Junction corridor to reopen between 15 and 20 December 2026, following the near completion of Phase One of the Greater Accra Resilient and Integrated Development (GARID) drainage improvement project.
Project Manager Cephas Ofori told Channel One News that the remaining tasks are backfilling and road pavement restoration. He said the goal is to ease congestion around the interchange during the Christmas season.
Ofori added that major construction activities – demolition, excavation, base wall construction and cover slab installation – have been finished. Phase Two, which extends from Pamprom Crossing to First Light, has already begun.
The westbound carriageway of the Dr Busia Highway at Pamprom Junction was closed on 7 September to allow the drainage works. The first closure phase was originally set to finish in November.
GARID Communications Specialist Philip Dunyo noted that public education and alternative routes have helped manage traffic. Motorists largely complied with the traffic arrangements, preventing major gridlock and keeping traffic moving.